One pilot, built to be repeated

We are developing a single project first and documenting it well enough that provincial partners, buyers, and funders can each check it. Expansion is gated on the pilot's measured results, not on ambition.

Current project

Status is stated as it is. No credits exist yet and none are for sale.

In feasibility

Punjab Native Afforestation Pilot

A 50-hectare native-species afforestation project on degraded land in Punjab, with site selection under way in the Chakwal and Rajanpur districts. Designed to Verra's Verified Carbon Standard for afforestation, with planting targeted for 2027 and validation planned for 2027–28.

Type
Afforestation, reforestation and revegetation (ARR), carbon removal
Scale
50 hectares, expandable in gated phases
Location
Punjab, Pakistan. Chakwal or Rajanpur district
Standard pathway
Verra VCS, ARR methodology. Not yet listed
Planting target
Second quarter, 2027
First issuance
Estimated 2032–34, five to seven years after planting
Project page →

Pipeline

What follows the pilot, and what has to be true first.

Phase 1 · 2026–28

Pilot, 50 hectares

Feasibility, land, planting, monitoring plots, and validation. This phase produces the survival and growth data everything else depends on.

Phase 2 · gated

Expansion, 500 hectares

Triggered only by a passed 24-month pilot review, a first verified issuance, and a signed offtake agreement. Additional sites in the same ecological zone, using the validated design.

Phase 3 · gated

Scale, 5,000+ hectares

Multiple sites across Punjab's ecological zones, each with its own tenure, baseline, and monitoring plots, grouped under the same programme and standard.

Following the pilot?

Buyers, funders, and land partners can register interest now and receive updates as the pilot passes each milestone.

Register interest